CSBP Kwinana

Project Value $14M

Proweld was engaged to install a new Ammonium Nitrate Bulk Load Out Facility at CSBP Kwinana. The project required Proweld to erect all free issue steel and mechanical equipment, plus workshop-fabricated pipework, electrical installation and cladding of main structure.

 

During this time, Proweld was responsible for coordinating with existing operating plant to safely plan tie in schedules with CSBP operators. Proweld started the project February 2014 and successfully completed the project by November 2014 which was on time and on schedule.